Step by Step Guide for Multiple Counter Plans

In this document we will be going through various steps involved to develop Multiple Counter Plan.
A multiple counter plan is used in counter based maintenance. This type of maintenance planning is not based on a maintenance strategy. This means that you can create a multiple counter plan without maintenance strategy.
Master data requirement
     Below are the list of basic Master data required to process Multiple Counter Plan.
      • Equipment
      • Characteristics for measuring point / counter
      • Measuring Point/Counter assigned to Equipment
      • Cycle sets as per requirement
Equipment – IE01 / IE02
     I have created PUMP as Equipment for explaining this scenario.
Test 1.jpg
Measuring Point / Counter – IK01
     We are going to record the running hours of the Pump. To record the running hours we need to create measuring point / counter.
Test 3.jpg
     Create the Measuring point for Equipment, enter the object type IEQ
     To make the measurement point as a Counter, you need to check “MeasPoint is counter”
   Ensure characteristics you want to assign to measuring point / counter were created
          Test 4.jpg
In the measuring counter, you need to maintain below fields                                                          
Header 1
Meas Position
Description
Characteristics
Counter Overflow reading
Annual Estimate
MeasPosition   – This describes the position of the measuring point / counter with respect to the Technical Object.
Counter Overflow reading – The first counter reading that the counter cannot display. Enter a logical value for the first counter reading.
Annual Estimate    – Estimated hours the equipment can run in a year. This needs to be filled, maintenance intervals are calculated based on this data.
On save, measuring point / counter is created.
Record the current running hours reading of the Pump using measuring documents (IK11), this is required to schedule the plan.
Test 5.jpg
On save, first measurement document created for measuring point / counter. Two documents are posted for this measuring point / counter.
Cycle Sets – IP11Z
     Cycle sets are used as a copy model for the creation of multiple counter plan. It defines the period of time between two maintenance tasks. Also cycle sets can be complied directly in multiple counter plan itself.
     Cycle sets needs to be created based on business requirement.
Test 6.jpg
Maintenance plan – IP01 / IP43
     Select the Maintenance plan category and Cycle set (Cycle set not mandatory)
Test 7.jpg
     Press Enter
     Cycle sets will be copied to the maintenance plan
 Cycle set sequence needs to be filled and same has to be linked to maintenance item. Here the scenario has only one cycle set sequence.
Cycle set sequence, Scheduling period, Start date will be populated in the multiple counter maintenance plan (IP43) after activating the “Configure Special Functions for Maintenance Planning” in SPRO.
     Kindly update the maintenance plan with relevant details like Maintenance Plan Description, Maintenance Item Description, Order Type, Planner Group, Work Center, Task list and Priority.
test 8.jpg
   Select the Maintenance plan scheduling parameters tab.
Test101.JPG
Kindly maintain the Sched Period and Start Date.
The important factor of Multiple Counter Plan is the Operation Type.
Kindly refer the scheduling column for the Operation type and difference on scheduling the maintenance plan.
On Save Maintenance Plan will be saved.
Scheduling – IP10 / IP30
On scheduling the plan, we need to consider the Operation Type and the behavior of scheduling will be different based on the type.
OR Operation Type:
For an OR Operation, a maintenance order is generated for the earliest possible planned date.
In our case, if the maintenance is due every 250 hrs or 3 months, the decisive factor is which occurs first.
Test 10.jpg
On scheduling the Maintenance plan
Test 11.jpg
Since the measuring counter reading is already reached 250, a maintenance is already due, on save, work order will be generated.
AND Operation type:
For an AND Operation, a maintenance order is generated for the last planned date.
In our case, if the maintenance is due every 250 hrs or 3 months, the decisive factor is which occurs last.
Test 12.jpg
On scheduling the maintenance plan
Test 13.jpg
Measuring counter is reached, but the 3 months is not reached so the maintenance is planned for the future date based on the start date.
Here I have covered the basic scenario of Multiple Counter Plan, there are lot of options available to explore in this area. 
(By: Maria Terence )